Title: NH Fuse Size Codes: Checking Blade and Base Compatibility Proposed slug: nh-fuse-size-blade-base-compatibility Focus keyword: nh fuse size blade base compatibility SEO title: NH Fuse Size and Base Compatibility Checklist | RITOKS SEO description: Check NH fuse size, blade interface, base or switch part number, ratings and enclosure clearance before approving a replacement link or new fused assembly. Excerpt: An NH size code is only the start of a blade-fuse fit check. Use this drawing and evidence checklist to match a link with its exact base or fuse switch.

Size-code check before ampere comparison
A standard fuse size is not determined by marked current alone. Two NH fuse-links can carry the same marked current while differing in body size, blade geometry, indicator or gripping arrangement, voltage rating and application. A base can have its own current and voltage limits, contact design, terminal provisions and mounting envelope. The procurement question is therefore not “Is this a 160 A fuse?” but “Is this exact link approved in this exact base or fuse-switch configuration, for this circuit and installation?”
The distinction matters especially when a maintenance team receives a substitute item after a panel has already been built. A blade that appears to enter the clips is not evidence of adequate contact pressure, acceptable heating, protective coordination or safe operation. Nor does a shared NH label make all numbered sizes interchangeable. The public description of IEC 60269-2 identifies a standardized NH blade-contact fuse system, but the standard overview is not a part-number cross-reference or a certification of a particular mixed-manufacturer assembly [1].
This guide treats compatibility as a documented interface decision. It is intended for qualified panel builders, procurement teams and maintenance engineers who can obtain the drawings and instructions for the exact products. It is not an instruction to install or replace a live fuse-link. Work methods and isolation procedures must follow the responsible site's rules and the device manufacturer's instructions.
Read the size code before comparing ratings
Start by recording the complete marking and order code from the link, then do the same for the base or switch. NH size codes such as 000, 00, 0, 1, 2 and 3 identify physical families, not a continuum in which the next larger size is an acceptable substitute. Some product ranges include additional sizes or variants. A catalogue may explicitly map a particular link size to a particular base part number; that mapping is more useful than a guess based on the ampere value.
Eaton's NH base data sheet, for example, lists separate base part numbers against compatible link body sizes 00, 1, 2 and 3, with different mounting variants and arrangements [2]. That is a documented mapping for Eaton's listed products. It does not prove that an unrelated link or switch with a similar code is approved without its own documentation. Eaton's fuse catalogue also shows that link drawings vary by size [3]. The lesson is the method: compare exact part numbers and dimensional drawings, not just catalogue headings.
The RITOKS RTX-NHG NH gG fuse-link page currently identifies an NH0 family reference and describes a blade-type gG link with model-specific electrical ratings [5]. It does not publish a full dimensional interface table or a universal mating-base list. The NH three-pole fuse-switch page lists switch sizes from NH000 through NH3 and says links are separate components [6]. These pages justify an inquiry about an exact pair; they do not justify claiming that RTX-NHG0 fits every switch in the range.
Compare the blade and contact system, not the silhouette
Ask for the fuse-link drawing and the base or switch assembly drawing. Confirm the size designation on both and inspect the dimensions that control the blade-to-contact interface: blade width and thickness, insertion length, spacing between blade centres, body clearance around the clips, and the location of gripping or operating features. A drawing's dimension labels must be read in the manufacturer's orientation; a top-view measurement cannot simply be substituted for the clip opening seen in an installed enclosure.
Next, inspect the contact architecture. An open NH base, a protected base, a fuse-switch disconnector and a busbar-mounted variant may secure or shield the fuse differently. Covers, barriers and link-replacement handles may need their own space. The Eaton data sheet lists separate single-pole, three-pole, mounting and accessory variants [2]. A common rated current among those variants does not collapse them into one mechanical interface. If a catalogue notes double contact clips, treat that as a variant that requires the stated link and accessory arrangement, not as permission to use an arbitrary blade.
A useful compatibility statement names both order codes and the configuration under which they were checked. “NH compatible” is too broad for an acceptance record. For a cross-supplier combination, request written confirmation or a documented compatibility list from the parties responsible for the equipment. If neither can confirm it, leave the substitute unapproved rather than treating a trial fit as a test of electrical adequacy.

Make a two-column evidence sheet
A short evidence sheet prevents a fuse procurement issue from becoming a field improvisation. Fill the left column from the existing installation and the right column from the proposed link or assembly. Mark every unresolved field as open.
| Field to record | Installed base or fuse switch | Proposed fuse-link |
|---|---|---|
| Identity | Manufacturer, complete part number and revision | Manufacturer, complete part number and revision |
| NH interface | Published compatible link size and contact variant | Published body size, blade drawing and lug arrangement |
| Circuit rating | Base or switch voltage/current and applicable duty | Link voltage/current, utilization category and breaking data |
| Mechanical space | Mounting form, clip position, cover and barriers | Body envelope, indicator and gripping clearance |
| Koneksi | Terminal type and conductor or busbar arrangement | Link's mating contact surfaces and any accessory conditions |
| Bukti | Assembly manual, drawing, approved-link list | Link data sheet, drawing and compatibility confirmation |
| Keputusan | Open, approved for stated pair, or rejected | Exact code and revision recorded in the decision |
The sheet deliberately separates the base rating from the link rating. An assembly is constrained by every component and by its application conditions. A base's current number does not define which protective characteristic the link provides, and a link's voltage number does not automatically authorize a switch's operating duty. The responsible engineer must assess the circuit protection and switching requirement using the exact data for each item.
Work through three substitution outcomes
The following hypothetical procurement example shows how the evidence sheet changes a buying decision. A panel schedule identifies an installed size-00 base, an approved gG link reference and a particular protective study. A distributor offers three alternatives, each advertised with the same ampere marking. No option below represents an actual RITOKS model or an approved cross-brand combination.
Candidate one is declared size 1. It fails the initial documented size screen for the stated size-00 base. Spending time comparing its time-current curve cannot resolve that mechanical mismatch. The buyer can either request the scheduled size-00 link or send a proposal for a different complete assembly to the engineer. Calling the larger link an upgrade would confuse physical family with electrical performance.
Candidate two is declared size 00 and has a drawing matching the interface fields, but its utilization category differs from the scheduled gG link. It has progressed further mechanically, yet it is not a direct protective substitute. The existing study was based on a particular characteristic, so the altered category requires an engineering decision. The buyer should describe the discrepancy explicitly rather than treating the base compatibility as approval of the protective function.
Candidate three is declared size 00 and gG, and its proposed order code appears in the base manufacturer's approved-link list. Its installed envelope, accessory arrangement and relevant circuit ratings also match the schedule. This is the strongest candidate for a direct replacement review. The evidence now supports a named pair, so procurement can check that the delivered revision is the documented one. If a cover or mounting variant has changed, the installation check still needs to address that change before release.
This example distinguishes three outcomes: a clear interface mismatch, a change requiring a protection review, and a documented candidate for acceptance. It also makes the sheet usable. A missing drawing belongs in an open field; a contradictory size belongs in a rejected field; an exact approved reference belongs in the confirmed evidence field. Those states should not be collapsed into a single “NH compatible” checkbox, because each leads to a different next action and different lead-time uncertainty.

Electrical match follows the mechanical match
After identifying a mechanically documented pair, verify the electrical selection. Confirm the supply type and voltage at the fuse location, continuous current and load behavior, prospective fault conditions, the specified link utilization category and the coordination requirement. A gG link is not interchangeable with a different utilization category simply because it shares an NH body size. The protection study may require a time-current curve, let-through or energy data, and a check against upstream and downstream devices. This article cannot provide that study for an unknown circuit.
Also separate the role of a fuse base from the role of a fuse switch disconnector. A base holds a link and forms part of the electrical connection; a switch disconnector has an operational switching function with its own documented utilization category and instructions. The RITOKS NH three-pole switch page publishes switching-category information separately from the selected fuse-link characteristics [6]. Do not infer that the fuse alone grants load-break capability, or that a switch rated for one duty can be operated under a different one. Obtain the exact switch manual and circuit data before specifying or operating it.
Check installation conditions that may alter the suitability of an otherwise correct pair. The enclosure temperature, close grouping of poles, airflow, terminal construction, conductor arrangement and accessory covers can affect thermal performance. Manufacturer data can include power-loss or temperature considerations, but the figures belong to the stated product and configuration. Do not import an Eaton base's derating or torque data into a RITOKS switch simply because both use NH links [2].
Cabinet space and service access are part of compatibility
A link may mate at the contact yet leave too little room to close the cover, read the indicator or use the prescribed replacement handle. Collect overall and installed dimensions for the exact assembly, including barriers, shrouds, cable bend and the enclosure door. Check whether the device mounts on a panel, a DIN rail or a busbar system. For a three-pole switch, verify the pole pitch and the installed wiring path rather than measuring only one loose fuse-link.
The RITOKS switch page lists both board-fixed configurations and a size-00 60 mm busbar option [6]. That is a meaningful mounting distinction. The presence of a busbar variant does not mean the ordinary board-fixed part will fit the same busbar, and the reverse is also true. Specify the mounting reference before ordering a matching link. If the current cabinet drawing is unavailable, obtain an as-built photograph and measured envelope, then check those observations against the official drawing. Photographs are useful for identifying the installation but should not replace controlled dimensions.
Service practice should be documented too. Mersen describes the NH system as a base, a blade-contact link and a replacement device, and warns that its design does not guarantee non-interchangeability by current rating [4]. That supports a simple procurement control: do not rely on the shape to prevent someone from fitting an electrically wrong current rating. Label the panel, preserve the approved part-number schedule and ensure replacement instructions identify the correct link. A spare-parts list should be versioned when an enclosure or switch is changed.
What to ask a supplier before accepting a substitute
Send the supplier the exact installed base or switch reference, proposed link reference, required ratings, enclosure/mounting arrangement and destination-market requirements. Ask for the dimensional drawing and a statement that the two references are approved together. If the supplier proposes a revised model, request the revision-to-revision difference and any change to covers, clips, indicator or operating handle. A verbal “same size” answer should remain provisional until the corresponding documentation is received.
For the RITOKS pairing, include the RTX-NHG link reference and the exact NH switch reference in one inquiry. The public link page gives an NH0 reference, while the switch page lists several sizes; the matching link for a selected switch has to be confirmed model by model [5][6]. Ask separately for the fuse-link electrical data and the switch's connection and operating instructions. This approach creates a traceable acceptance record without inventing a compatibility matrix that the public site does not provide.
If an urgent replacement has no documentary match, do not turn the urgency into a physical-fit exception. Record the unresolved issue and use the site's authorized engineering and maintenance process. The outcome may be a confirmed exact substitute, a different approved assembly, or a delay until correct parts arrive. The article's purpose is to make that decision auditable, not to pre-approve a product unseen.
Approve the exact link and base references
An NH code narrows the search; it does not finish it. Approve a proposed fuse-link/base pair only after the exact order codes, drawings, contact interface, installation envelope and electrical ratings are documented for the actual circuit. Keep the protection study and the switch operating duty separate from the mechanical fit check. When a link and switch are sold as related products, request a specific compatibility statement rather than inferring one from the category page. The result should be a named, evidence-backed assembly and a clear replacement schedule for the people who will service it later.
Source notes
- IEC, IEC 60269-2:2013, standard overview identifying the NH blade-contact system.
- Eaton Bussmann, NH Bases technical data 10163, December 2024, compatibility tables and dimensional drawings.
- Eaton Bussmann, NH fuse-links, bases and gear catalogue, April 2025, fuse-link size drawings.
- Mersen, NH000 gG fuse-link product description, system components and current-rating non-interchangeability warning.
- RITOKS, RTX-NHG NH gG Tautan Sekring, public family and model information accessed 2026-09-30.
- RITOKS, Pemutus Arus Sekring 3-Polar NH, public size and mounting options accessed 2026-09-30.