AC Power Protection · Technical Explainer
AC Protection Panel RFQ: Fault Level, Poles and Device Schedule
An AC distribution-panel quotation becomes difficult when the only description is “three-phase panel with breakers.” That phrase leaves the prospective fault current, system voltage, earthing arrangement, circuit list, conductor capacity and device functions undefined. Even a catalog breaker with a familiar current rating can be unsuitable at the point where it will be installed. A useful RFQ separates the project electrical data from the proposed device schedule, then asks the supplier to document each exact model at its intended duty.

RITOKS publishes AC miniature circuit breakers and a separate GYCM8 molded-case breaker family. The families have different frame, pole, trip and breaking-capacity choices. They are components for a qualified panel design, not a promise that RITOKS supplies a complete certified switchboard or that any two devices form a verified coordinated pair. This guide helps a panel buyer prepare a schedule that can be answered without inventing a site fault level.
| RFQ layer | Buyer-provided information | Supplier/model confirmation |
|---|---|---|
| System | Voltage, phases, frequency, earthing and supply source | Device ratings at that voltage |
| Fault duty | Prospective short-circuit current at each location | Exact breaking-capacity table and coordination evidence |
| Circuit | Load, conductor, poles, switching and protection purpose | Model, trip characteristics and terminals |
| Panel | Enclosure, mounting, heat and access constraints | Mechanical drawings and installation instructions |
The schedule is an information model, not a circuit design. A licensed or otherwise qualified engineer determines ratings under applicable rules.
State the Electrical System Before the Breakers
Record nominal line-to-line and line-to-neutral voltage, phase arrangement, frequency, earthing system and supply transformer or upstream source. Include any generator, inverter or transfer arrangement that changes available fault current or operating conditions. A breaker rating published for one voltage does not automatically apply at another. On the GYCM8 product page, rated operational voltage and capacity are explicitly model- and pole-dependent.
Prepare a current single-line diagram and a circuit schedule rather than a photograph alone. Number each incoming, feeder and final circuit; identify its load and intended protective function. State the required applicable standard and market. If the panel is a retrofit, provide the existing board's documented ratings and spare-way arrangement. Do not assume an old label gives the present prospective short-circuit current after a utility or transformer change.
Separate the equipment that protects a branch from equipment that switches a motor, protects against surges or measures current. A molded-case circuit breaker, a miniature breaker, a motor-protection circuit breaker and a surge protective device have different roles. A generic “breaker” line in a BOM hides those distinctions and can lead to an incorrect substitute.
Put Fault Level at the Device Location
Prospective short-circuit current is a property of the installation point and upstream impedance, not a property of the load's normal amperage. The buyer's qualified designer should calculate or provide it for the incoming section and relevant downstream circuits. Schneider Electric's breaker-selection FAQ says breaking capacity should be at least the calculated short-circuit current for the supply feeder in its example. That is a general selection principle; the project design must still determine which rating definition and conditions apply.
Avoid requesting “10 kA breakers for the entire panel” without a fault study. The RITOKS catalog contains MCB families with differing published breaking capacities, and GYCM8 uses frame-, pole- and voltage-specific Icu and Ics capacity tables. A rating attached to a different model or voltage row cannot be copied to the planned device. If a proposed downstream device relies on a manufacturer-tested back-up or cascading combination, request the exact pair and documented conditions. Do not infer series protection from visual similarity.

The panel's overall short-circuit withstand or rating is another design-level item. It cannot be derived from the highest-rated breaker alone. Busbars, conductors, terminals, enclosure assembly and incoming arrangements must be assessed under the applicable standard. This guide does not certify a complete panel from individual component pages.
Specify Poles and Neutral Behavior Explicitly
“Two poles” and “1P+N” are not automatically equivalent. A 1P+N arrangement may switch both paths but protect only the phase pole, depending on the exact device; a true 2P product has its own documented function. The load, earthing arrangement and isolation requirement decide what conductors must be switched or protected. RITOKS has a published 1P+N vs 2P buyer guide that treats the distinction as a configuration question, not an interchangeable label.
List pole count and neutral treatment for each circuit. Include three-phase feeders, single-phase branches and any three-phase plus neutral loads separately. Do not assume the pole options of one GYCM8 frame apply to another: its published table has frame-specific 1P through 4P availability. Similarly, the RITOKS MCB families differ in 1P, 1P+N, 2P, 3P, 3P+N and 4P options. The actual chosen catalog number must be checked.
Where isolation or emergency switching matters, ask for the exact device's suitability and operating instructions. Pole count by itself does not prove a safety isolation function. The panel designer must reconcile device choice with the intended supply and neutral topology.
Keep MCB, MCCB and Motor Protection Distinct
The MCB category is a starting point for final-circuit and compact distribution choices. Its products have exact current, trip-curve, pole and capacity rows. The MCCB category supports a separate frame and breaking-capacity discussion for feeders and power distribution. Neither category title alone determines the panel's correct incoming device.
Motor circuits introduce start-up current, overload protection, switching and control requirements. A standard MCB or MCCB should not be relabeled as a motor-protection breaker merely because it is upstream of a motor. If the project includes a motor branch, identify the motor data and required functions before choosing MPCB or a verified alternative architecture. Keep device selection and starter coordination in the engineer's scope.
Likewise, a Type 2 AC surge protective device addresses transient overvoltage, not branch overcurrent. If included, its topology, continuous operating voltage, protection level and upstream protective requirements should be separately scheduled and supported by exact manufacturer documents. It should not be counted as an MCB replacement or assigned a breaker capacity from its discharge-current label.
Build the Device Schedule Row by Row
Each line should identify location, circuit designation, electrical function, normal load current, system voltage, poles and neutral behavior, target trip or adjustment characteristic, required breaking capacity at the operating voltage, mounting and terminal constraints, and quantity. A column for “document supplied” helps distinguish a model that is confirmed from one that is merely proposed. Leave an unresolved field blank with an action owner rather than inventing it.
For a GYCM8 candidate, record frame, exact current option, poles, voltage and the applicable Icu/Ics row. For an MCB candidate, record exact series, current rating, trip curve, pole configuration and published capacity. An AC MCB RFQ checklist can help with its branch, but it does not replace the panel-wide fault-level and coordination study.

Accessories need their own line. An auxiliary contact, shunt release or other option should be paired with the exact device variant and verified accessory documentation. A photograph showing an accessory near a breaker is not compatibility evidence. The request should state whether status, remote trip, lockout or another function is required, then ask the supplier to identify a documented combination.
Request Coordination Evidence, Not Just Two Ratings
Upstream and downstream breakers may both have breaking capacities adequate for their installation points but still trip together for a downstream fault. Selectivity or discrimination needs comparison of time-current behavior and manufacturer-tested combination data. ABB's selectivity guidance explains that achievable selectivity depends on device characteristics and fault levels. The engineering study should identify which circuits require continuity after a downstream fault and at what current range.
Do not call a pair “selective” because one has a larger rated current, a different frame or a delayed trip label. If a manufacturer coordination table is supplied, verify the exact product codes, voltage, settings and stated limit. Where no tested data is available, keep the coordination requirement open. A supplier should be able to distinguish a standalone device rating from a documented pair performance.
This is especially important for critical production or monitoring circuits, but the RFQ should state the continuity requirement rather than rely on a generic “industrial panel” description. A buyer who specifies the actual circuits and fault study makes the supplier response auditable.
A Practical Panel RFQ Packet
Provide a controlled packet with:
- Current single-line drawing, system voltage, phases, frequency, earthing and source details.
- Prospective fault-current values at the relevant locations, with calculation ownership and date.
- Circuit/device schedule with function, normal load, poles, neutral behavior and required ratings.
- Available panel space, mounting rail or plate, busbar and terminal constraints, environment and service access.
- Required coordination or back-up-protection evidence for named device pairs.
- Exact-model datasheets, certification or test documentation needed for the destination market.
- Quantities, delivery destination, drawing revision and unresolved questions.
Ask the supplier to mark every proposed row against the drawing revision. That prevents a late model substitution from silently changing the fault or pole assumptions. Keep an “approved by designer” status separate from a commercial price quote. The package gives a structured conversation; it is not a construction-ready panel design.
Selection Summary
An effective AC protection-panel RFQ names the electrical system, calculated fault duty, pole and neutral requirements, and each device's distinct job. The RITOKS AC Power Protection range is a catalog starting point, while the MCB and MCCB pages supply different product branches. Send the reviewed schedule through RITOKS contact for exact-model evidence, and let the qualified panel designer close the protection and assembly decisions.
Source notes
- RITOKS AC Power Protection, MCB and GYCM8 MCCB: current product-family boundaries and model-dependent ratings.
- Schneider Electric prospective-fault-current FAQ: general breaking-capacity selection principle.
- ABB selectivity guidance: coordination depends on tested device characteristics and fault range.